Federal Correctional Institution
El Reno, OK
Installation of New Central Standby Generator, Phase I & II
Government Agency: Federal Bureau of Prisons
Contract Number:
-
Phase I – DJBP0507S9F70001
-
Phase II – 15B50718CT2K80001
Prime contractor: 100% self-performed
Completion Date:
-
Phase I – 12/05/2018
-
Phase II – 07/06/2020
Contract Amount:
-
Phase I – $2,144,538
-
Phase II – $2,407,678
Scope of Work
Phase I:
-
Complete new 55’ x 65’ metal building to house new standby generator. Building installation included concrete foundation, HVAC system, lighting, fire alarm, fire suppression system, detention doors, overhead doors, and metal louvers.
-
Provided new 3000A 15KV paralleling switchgear and control modifications with existing S&C switches.
-
Completed overcurrent protective device coordination studies as well as arc flash studies.
-
Installed approximately 700 linear feet of 15KV primary cables in duct bank.
-
Installed (2) manhole vaults.
Phase II:
-
Provided and installed new medium voltage 3000KW backup generator for the facility.
-
Complete installation of new 5KV switchgear.
-
Two (2) new 600KVAR 15KV capacitor banks.
-
New neutral ground resistor.
-
Coordinated with S&C to provide new 15KV switch.
-
Installed new exhaust ductwork for the generator.
-
Provided control dampers for the building louvers and integrated with the generator for complete automation.