top of page
Generator room with two generators in factory standby for power backup, Diesel generator_e

Federal Correctional Institution

El Reno, OK

Installation of New Central Standby Generator, Phase I & II

Government Agency: Federal Bureau of Prisons
Contract Number:

  • Phase I – DJBP0507S9F70001

  • Phase II – 15B50718CT2K80001

Prime contractor: 100% self-performed
Completion Date:

  • Phase I – 12/05/2018

  • Phase II – 07/06/2020

Contract Amount:

  • Phase I – $2,144,538

  • Phase II – $2,407,678

Scope of Work

Phase I:

  • Complete new 55’ x 65’ metal building to house new standby generator. Building installation included concrete foundation, HVAC system, lighting, fire alarm, fire suppression system, detention doors, overhead doors, and metal louvers.

  • Provided new 3000A 15KV paralleling switchgear and control modifications with existing S&C switches.

  • Completed overcurrent protective device coordination studies as well as arc flash studies.

  • Installed approximately 700 linear feet of 15KV primary cables in duct bank.

  • Installed (2) manhole vaults.

Phase II:

  • Provided and installed new medium voltage 3000KW backup generator for the facility.

  • Complete installation of new 5KV switchgear.

  • Two (2) new 600KVAR 15KV capacitor banks.

  • New neutral ground resistor.

  • Coordinated with S&C to provide new 15KV switch.

  • Installed new exhaust ductwork for the generator.

  • Provided control dampers for the building louvers and integrated with the generator for complete automation.

bottom of page