Huntington, MA

Government Agency:  United States Army Corps of Engineers
Prime Contractor - Self Performed
Completion Date: In Progress
Contract Amount: $367,000.00

Scope of Work

•   Update the electrical distribution system which was outdated and needed replaced.  Replaced the utility poles and main transformer.
•    Demolish six existing utility poles and associated conductors located along the groin of the downstream sloap embankment. 
•    Install new buried feeder and buried communication line.
•    Demolish existing medium voltage transformer located near the flood control gatehouse.  Install new medium voltage transformer.
•    Replace feeder, primary service disconnect, transformer, secondary disconnect and panelboard at the project office and water control building.